Keywords: Causes, delay, construction project, industry, Libya
Abstract: This study focuses on determining the factors contributing to project delay in general and identified the top ten factors that lead delays in in the city of Al-Abyar, Libya. Date was collected through questionnaire survey, 73 questionnaires were sent out to project managers, contractors and consultants in the above-mentioned city, of these only 62 completed questionnaires were returned and analyzed, yielding a response rate 85%. As results, these factors are lack of skilled labour, poor communication and coordination, contractor’s poor site management, mistakes during the construction stage, equipment availability and failure and problems with subcontractors. Several strategies to mitigate these factors were recommends, such as providing regular meetings and clear communication channels can achieve effective communication and coordination. These recommendations can provide practical insights for practitioners and policymakers in the construction industry to mitigate the impact of cost overruns and delays.
References
Fashina, A.A., Omar, M.A., Sheikh, A.A., & Fakunle, F.F. (2021). Exploring the significant factors that in construction projects in Hargeisa, Heliyon, 7, https://doi.org/10.1016/j.heliyon.2021.e06826Al-Ghafly M.A. (1995). Delays in the construction of public utility projects in Saudi Arabia”, Master
thesis, CEM Dept., KFUPM, Dhahran, Saudi Arabia.
Durdyev, S., & Hosseini, M.R. (2020). Causes of Delays on construction projects: a comprehensive list,
International Journal of Managing Projects in Business, 13, 20-46.
relationship:
Tariq, J., & Gardezi, S.S.S. (2023). Study the delays and conflicts for construction projects and their
mutual
A review, Ain Shams Engineering Journal, 14, 1-14,
https://doi.org/10.1016/j.asej.2022.101815
Elziny, A.A., Mohamadien, M.A., Ibrahim, H.M., & Abdel Fattah, M.K. An expert system to manage
dispute resolutions in construction projects in Egypt, Ain Shams Engineering Journal, 7(1): 2016, pp.
57–71. doi: https://doi.org/10.1016/j.asej.2015.05.002.
Derakhshanfar, H., Ochoa, J.J., Kirytopoulos, K., Mayer, W., & Tam, V.W.Y. (2019). Construction
delay risk taxonomy, associations and regional contexts: a systematic review and meta- analysis,
Engineering, Construction and Architecture Management, 26(10): 2364–2388.
Assaf, S.A., Kalil, M., & Al-Hazmi, M. (1995). Causes of delay in large building construction projects,
Journal of Management in Engineering, 11(2): 45-50.
Alrasheed, K., Soliman, E., & Albader, H. (2023). Systematic review of construction project delays in
Kuwait, Journal of Engineering Research, 11, 347–355. https://doi.org/10.1016/j.jer.2023.08.009
Ogunlana, S.O., Promkuntong, K., & Jearkjirm, V. (1996). Construction Delays in Fast-Growing
Economy: Comparing Thailand with Other Economies, International Journal of Project Management,
14(1): 37-45.
Kaming, P.F., Olomolaiye, P.O., Holt, G.D., & Harris, F.C. (1997). Factors influencing construction
time and cost overruns on highrise projects in Indonesia. Construction Management and Economics,
15, 83-94.
Mezher, T.M., & Tawil, W. (1998). Causes of Delays in the Construction Industry in Lebanon,
Engineering Construction and Architectural Management Journal, 5(3): 251-60.
Akogbe, R. K. T., Feng, X., and Zhou, J. (2013). Importance and ranking evaluation of delay factors
for development construction projects in Benin, KSCE Journal of Civil Engineering, 17(6): 1213–1222.
Kazaz, A., Ulubeyli, S., & Tuncbilekli, N.A. (2012). Causes of delays in construction projects in
Turkey. Journal of Civil Engineering and Management, 18(3): 426–435.
Hussin, A.A., & Omran, A. (2011). Implication of Non-Completion Projects in Malaysia, ACTA
Technica Corviniensis-Bulletin of Engineering, 4(4): 29-38.
Nachatar, J.S., Hussin, A.A., Omran, A. (2011). Frustration of Contract in the Malaysian Construction
Contract Management, Annals of the Faculty of Engineering Hunedoara, 9(3): 85-90.
Kumaraswamy, M.M., & Chan, D.W.M. (1998). Contributors to construction delays, Construction
Management and Economics, 16(1): 17–29.
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003). Causes of Delay and Cost Overruns in Construction
of Groundwater Projects in a Developing Countries, Ghana as a case study, International Journal of
Project Management, 21, 321-326.
Mansfield, N.R., Ugwu, O.O., & Doran, T. (1994). Causes of delay and cost overruns in Nigeria
construction projects, International Journal of Project Management, 12(4): 254-260.
Odeh, A.M., & Battaineh, H.T. (2002). Causes of construction delay: traditional contracts, International
Journal of Project Management, 20, 67-73.
Niazi, G.A. & Painting, N. (2017). Significant Factors Causing Cost Overruns in the Construction
Industry in Afghanistan, 7th International Conference on Engineering, Project, and Production
Management, Procedia Engineering, 182, 510 – 517.
Long, D.N., Ogunlana, S.O., Quang, T. & Lam, K.C. (2004). Large Construction Projects in Developing
Countries, a Case Study from Vietnam, International Journal of Project Management, 22, 553-561.