Home \ Archives\vol 1, No 1, 2025\ Articles
FACTORS CAUSING DELAYS IN THE CONSTRUCTION INDUSTRY IN THE CITY OF AL-ABYAR, LIBYA
- ABDELWAHAB OMRAN GEBRIL & ABDULKARIM EMRAN JIBREEL ALI
- University of Benghazi, Al-Abyar Branch, Libya
DOI: 10.64587/NSJAPGSagaa
Volume (1), Issue (1) , June 2025

Published: 06/30/2025
Keywords: Causes, delay, construction project, industry, Libya
Abstract: This study focuses on determining the factors contributing to project delay in general and identified the top ten factors that lead delays in in the city of Al-Abyar, Libya. Date was collected through questionnaire survey, 73 questionnaires were sent out to project managers, contractors and consultants in the above-mentioned city, of these only 62 completed questionnaires were returned and analyzed, yielding a response rate 85%. As results, these factors are lack of skilled labour, poor communication and coordination, contractor’s poor site management, mistakes during the construction stage, equipment availability and failure and problems with subcontractors. Several strategies to mitigate these factors were recommends, such as providing regular meetings and clear communication channels can achieve effective communication and coordination. These recommendations can provide practical insights for practitioners and policymakers in the construction industry to mitigate the impact of cost overruns and delays.
References
Al-Ghafly, M. A. (1995). Delays in the construction of public utility projects in Saudi Arabia (Master’s thesis). Construction Engineering and Management Department, KFUPM, Dhahran, Saudi Arabia.
Alrasheed, K., Soliman, E., & Albader, H. (2023). Systematic review of construction project delays in Kuwait. Journal of Engineering Research, 11, 347–355. https://doi.org/10.1016/j.jer.2023.08.009
Akogbe, R. K. T., Feng, X., & Zhou, J. (2013). Importance and ranking evaluation of delay factors for development construction projects in Benin. KSCE Journal of Civil Engineering, 17(6), 1213–1222.
Assaf, S. A., Kalil, M., & Al-Hazmi, M. (1995). Causes of delay in large building construction projects. Journal of Management in Engineering, 11(2), 45–50.
Derakhshanfar, H., Ochoa, J. J., Kirytopoulos, K., Mayer, W., & Tam, V. W. Y. (2019). Construction delay risk taxonomy, associations, and regional contexts: A systematic review and meta-analysis. Engineering, Construction and Architectural Management, 26(10), 2364–2388.
Durdyev, S., & Hosseini, M. R. (2020). Causes of delays on construction projects: A comprehensive list. International Journal of Managing Projects in Business, 13, 20–46.
Elziny, A. A., Mohamadien, M. A., Ibrahim, H. M., & Abdel Fattah, M. K. (2016). An expert system to manage dispute resolutions in construction projects in Egypt. Ain Shams Engineering Journal, 7(1), 57–71. https://doi.org/10.1016/j.asej.2015.05.002
Fashina, A. A., Omar, M. A., Sheikh, A. A., & Fakunle, F. F. (2021). Exploring the significant factors that affect construction projects in Hargeisa. Heliyon, 7, e06826. https://doi.org/10.1016/j.heliyon.2021.e06826
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003). Causes of delay and cost overruns in construction of groundwater projects in developing countries: Ghana as a case study. International Journal of Project Management, 21, 321–326.
Hussin, A. A., & Omran, A. (2011). Implication of non-completion projects in Malaysia. ACTA Technica Corviniensis – Bulletin of Engineering, 4(4), 29–38.
Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997). Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Construction Management and Economics, 15, 83–94.
Kazaz, A., Ulubeyli, S., & Tuncbilekli, N. A. (2012). Causes of delays in construction projects in Turkey. Journal of Civil Engineering and Management, 18(3), 426–435.
Kumaraswamy, M. M., & Chan, D. W. M. (1998). Contributors to construction delays. Construction Management and Economics, 16(1), 17–29.
Long, D. N., Ogunlana, S. O., Quang, T., & Lam, K. C. (2004). Large construction projects in developing countries: A case study from Vietnam. International Journal of Project Management, 22, 553–561.
Mansfield, N. R., Ugwu, O. O., & Doran, T. (1994). Causes of delay and cost overruns in Nigerian construction projects. International Journal of Project Management, 12(4), 254–260.
Mezher, T. M., & Tawil, W. (1998). Causes of delays in the construction industry in Lebanon. Engineering, Construction and Architectural Management, 5(3), 251–260.
Nachatar, J. S., Hussin, A. A., & Omran, A. (2011). Frustration of contract in the Malaysian construction contract management. Annals of the Faculty of Engineering Hunedoara, 9(3), 85–90.
Niazi, G. A., & Painting, N. (2017). Significant factors causing cost overruns in the construction industry in Afghanistan. Procedia Engineering, 182, 510–517. https://doi.org/10.1016/j.proeng.2017.03.145
Odeh, A. M., & Battaineh, H. T. (2002). Causes of construction delay: Traditional contracts. International Journal of Project Management, 20, 67–73.
Ogunlana, S. O., Promkuntong, K., & Jearkjirm, V. (1996). Construction delays in a fast-growing economy: Comparing Thailand with other economies. International Journal of Project Management, 14(1), 37–45.
Tariq, J., & Gardezi, S. S. S. (2023). Study of delays and conflicts for construction projects and their mutual relationship: A review. Ain Shams Engineering Journal, 14, 1–14. https://doi.org/10.1016/j.asej.2022.101815
Abd El-Razek, M. E., Bassioni, H. A., & Mobarak, A. M. (2008). Causes of delays in building construction projects in Egypt. Journal of Construction Engineering and Management, 134(11), 831–841.
Al-Khalil, M. I., & Al-Ghafly, M. A. (1999). Important causes of delays in public utility projects in Saudi Arabia. Construction Management and Economics, 17(5), 641–655.
Assaf, S., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349–357.
Burns, R. (1994). Interdisciplinary teamed instruction: Development and pilot test. Charleston, WV: Appalachia Educational Laboratory.
Faridi, A. S., & El-Sayegh, S. M. (2006). Significant factors causing delay in the UAE construction industry. Journal of Construction Engineering and Management, 132(11), 1167–1176.
Fugar, F. D. K., & Agyakwah, B. A. B. (2010). Delays in building construction projects in Ghana. Australasian Journal of Construction Economics and Building, 10(1–2), 103–116.
Hatush, Z., & Skitmore, M. (1997). Evaluating contractor prequalification data: Selection criteria and project success factors. Construction Management and Economics, 15(2), 129–147.
Kometa, S. T., Olomolaiye, P. O., & Harris, F. C. (1994). Attributes of UK construction clients influencing project consultants’ performance. Construction Management and Economics, 12(5), 433–443.
Lim, E. C., & Alum, J. (1995). Construction productivity: Issues encountered by contractors in Singapore. International Journal of Project Management, 13(1), 51–58.
Lo, T. Y., Fung, I. W., & Tung, K. C. (2006). Construction delays in Hong Kong civil engineering projects. Journal of Construction Engineering and Management, 132(6), 636–649.* https://doi.org/10.1061/(ASCE)0733-9364(2006)132:6(636)
Mahamid, I. (2011). Risk matrix for factors affecting time delay in road construction projects: Owners’ perspective. Engineering, Construction and Architectural Management, 18(6), 609–617.
Omran, A. (2015). Determining the factors affecting the performance of construction projects in Libya. Journal of Academic Research in Economics, 7(2), 211–219.
Omran, A., Bamidele, O., & Baharuddin, A. H. B. (2016). Causes and effects of incessant building collapse in Nigeria. Serbian Project Management Journal, 6(1), 13–26.
Omran, A., Ling, O. A., Pakir, A. K., & Ramli, M. (2010). Delay factors in construction projects development: The case of Klang Valley, Malaysia. International Journal of Economic Research, 2(2), 45–53.*
Omran, A., Salleh, M. S. H., & Abdelwahab, O. G. (2023). Determining factors causing time and cost overruns of construction projects in Malaysia. Design, Construction, Maintenance, 3, 179–186.
Omran, A., Salma, A., & Pakir, A. K. (2012). Project performance in Sudan construction industry: A case study. Academic Research Journals, 1(1), 55–78.
Pourrostam, T., & Ismail, A. (2011). Significant factors causing and effects of delay in Iranian construction projects. Australian Journal of Basic and Applied Sciences, 5(7), 450–456.
Sambasivan, M., & Soon, W. Y. (2007). Causes and effects of delay in Malaysian construction industry. International Journal of Project Management, 25, 517–526.
Sweis, G., Sweis, R., Abu Hammad, A., & Shboul, A. (2008). Delays in construction projects: The case of Jordan. International Journal of Project Management, 26(6), 665–674.
Teo, S. P., Omran, A., & Pakir, H. K. (2009). Material wastage in Malaysian construction industry. Proceedings of the International Conference on Economic and Administration, Faculty of Administration, University of Bucharest, Romania, 257–264.
Tumi, S. H., Omran, A., & Pakir, A. H. K. (2009). Causes of delay in construction industry in Libya. Proceedings of the International Conference on Economics and Administration, Faculty of Administration and Business, University of Bucharest, Romania, November 14–15.
Walker, H. T., & Vines, M. W. (2000). Australian multi-residential project construction time performance factors. Construction Engineering and Architectural Management, 7(3), 278–284.